Paver calculator

Enter the patio size and the paver you are buying. You get the paver count, and — the part most calculators leave out — the aggregate base, which outweighs the pavers themselves and has to be dug wider than the patio.

Pavers to buy 473 pavers Includes the waste allowance, rounded up. Buy them in one delivery — colour varies between production batches.
Pavers per square foot 4.5 per sq ft
Base gravel to order 1.87 cu yd Loose volume, compaction allowance included.
Base gravel by weight 2.75 tons At 2,950 lb/cu yd for crusher run. Ask your quarry for its own figure — that is what the ticket is priced on.
Area to excavate 121 sq ft Larger than the patio, because the base has to run past the edge restraint.
Bedding sand volume 8.3 cu ft A nominal 1 in screeded bed. For bag counts and joint sand, use the [paver sand calculator](/calculators/paver-sand).
Weight of the pavers 2,793 lb The patio as designed, before the waste allowance. Paver concrete is about 142 lb/cu ft.

How the count is worked out

Pavers per square foot is 144 divided by the paver's area in square inches. A 4 x 8 module is 32 sq in, so 4.5 pavers per square foot. A 10 ft x 10 ft patio is 450 pavers before waste, 473 with 5% for cuts.

Nominal or actual size? Neither answer is always right

Every calculator page tells you to ignore the nominal size and divide by the real one. That advice is wrong about half the time, and here is why.

Pavestone's 60 mm Holland stone actually measures 7.87 x 3.94 in (200 x 100 mm). The ICPI/CMHA construction specification calls for joints between 1/16 and 3/16 in (2–5 mm) wide, and 7.87 in plus a 3 mm joint is 7.99 in — the stone is designed so that unit plus joint fills an 8 x 4 in module. Divide by the module and you get 4.5/sq ft, which is correct for the laid pavement.

Divide by the bare face instead and you get 4.66/sq ft. That is also a real number: it is what the pallet label says, because 480 pieces covering 103 sq ft counts face area with no joint allowance. It is the more conservative order by about 3.5%.

So: use whichever figure your product sheet gives you — published coverage, or actual dimensions plus your joint width. Do not apply a blanket "always use the actual size" rule, and do not mix the two.

The related myth is that certain patio dimensions force cuts. They don't, by themselves — 12 ft is 144 in, which divides evenly by both 4 and 8. Cuts come from the pattern: a 45° layout or herringbone leaves a triangular offcut at every border that cannot be turned around and used on the other side, which is why those patterns need 10–15% instead of 5%.

The base is the bigger material order

Weigh a 10 x 10 patio: the 60 mm pavers come to about 1.4 tons, and the 4 in compacted base under them is about 2.8 tons. Most paver calculators return only the paver count and call that a material list. Two things drive the base number:

  1. Compaction. Loose crushed stone carries 35–40% air voids and compacts to 20–25%, so a dense-graded base is ordered about 25% over the finished volume. Place it in lifts, not one deep layer.
  2. Extent. CMHA Tech Spec 3 states that "the base should extend beyond the restraint at least the same dimension as the thickness of the base material." For a 10 x 10 patio, adding 6 in on each side means excavating 121 sq ft, not 100 — a 21% jump. Skimp on it and the edge restraint spikes sit in soil, the perimeter drops, and the whole field walks outwards.

The same Tech Spec is blunt on two related points: edge restraints must never be installed on top of the bedding sand, and soil backfill is never a suitable edge restraint.

What this leaves to other pages

Bedding sand is quoted here as a volume only — the paver sand calculator does bags, and joint sand by joint width. Base depth minimums are ICPI/CMHA: 4 in compacted for patios and walkways over well-drained soil, 6 in for a residential driveway, and 80 mm pavers rather than 60 mm wherever a vehicle will drive.

Common cases

Questions people ask

How many 4x8 pavers per square foot?
Four and a half. A 4 x 8 module is 32 square inches and there are 144 in a square foot. Pallet labels often quote about 4.66/sq ft instead — for example 480 pieces over 103 sq ft — because pallet coverage measures the paver face and ignores the joint. Either is defensible; do not mix them.
How many pavers do I need for a 10x10 patio?
473 of the common 4 x 8 size: 100 sq ft at 4.5 per sq ft is 450, plus 5% for cuts. At 12 x 12 it is 105. Order everything at once — concrete pavers are produced in batches and the colour shifts between them, so a top-up delivery rarely matches.
How much gravel base do I need under pavers?
Four inches compacted for a patio or walkway over well-drained soil, six for a residential driveway, per the ICPI/CMHA specification. Order 20–25% more than that finished volume because crushed stone loses that much under the plate compactor, and dig 6 in wider than the paving on every side.
Do I need to compact the base before laying pavers?
Yes, in lifts. A 4 in base placed in one go stays loose underneath no matter how long you run the plate over the top, and that lower half is what settles in year two. Compact each lift, then screed the sand — never use the bedding sand to fill dips in the base.
How much does a paver patio weigh?
A 60 mm paver runs about 28 lb per square foot, so a 10 x 10 patio is roughly 1.4 tons of stone, and the base under it another 2.8 tons. That figure comes from published pallet data — 480 pieces at about 2,884 lb — and it is worth checking against your vehicle before you plan to haul it yourself.
How much extra should I order for a herringbone pattern?
Ten percent for 90° herringbone and 10–15% at 45°. The extra is not breakage, it is geometry: a diagonal border cut produces a triangular offcut that will not fit anywhere else on that border. Running bond parallel to the edges can get away with 5%.