HowMuch

Concrete footing calculator

Pick the footing shape, enter the dimensions, and this gives you the concrete plus the rebar you actually have to buy — including the overlap at every splice, which is not optional and is not free.

Concrete needed 0.72 cu yd
Same volume in cubic feet 19.6 cu ft
Bags of mix 33 bags Rounded up. Past about one cubic yard, price a short load of ready-mix instead.
Finished weight 2,933 lb
Rebar in place, laps included 40 ft Strip and pad footings only. A round pier normally takes a vertical dowel, not a continuous run.
Rebar sticks to buy 2 pieces 20 ft lengths.

Three shapes, one formula

A strip footing under a wall and a pad under a post are the same sum: length × width × depth. A round deck pier is π × radius² × depth. The answer comes back in cubic yards because that is how ready-mix is sold — 27 cubic feet to a cubic yard, not 3.

A 20 ft strip footing 16 in wide and 8 in deep is 17.8 cubic feet. Add 10% for a trench dug in earth and you are ordering 0.72 cubic yards, which is 33 × 80 lb bags. Bag yields are QUIKRETE's published figures for general-purpose concrete mix: 80 lb → 0.60 cu ft, 60 lb → 0.45, 50 lb → 0.375, 40 lb → 0.30.

The rebar mistake: laps are not free

Rebar comes in 20 ft sticks. Where two sticks meet they have to overlap, and the overlap length is set by code. IRC Table R608.5.4(1) gives the tension lap splice for Grade 60 bar as 30 in for #4, 38 in for #5 and 45 in for #6.

Almost every footing calculator divides the run by 20 and stops. On the 96 ft perimeter of a 24 × 24 ft garage that gives five sticks per run. The real answer is six: the first stick covers 20 ft, but every stick after it only adds 20 − 2.5 = 17.5 ft of new footing. Two runs of bar, and you are two sticks short — which you discover with the trench dug and the truck booked.

Watch the grade, too. The "40 bar diameters" figure repeated all over the web is the Grade 40 column of that same table. Grade 60 is what you actually buy, and its lap is 60 bar diameters. Using the Grade 40 number makes every splice a third too short.

Corner bars are not counted here. Where two runs meet, the bars have to be tied round the corner with a bent or L-shaped bar lapped into both runs — add one lap length per leg, per corner.

What the code actually asks for

Bags or a truck

The crossover sits right inside the range people search for. A 20 ft footing at 0.72 cubic yards is under the 1 cubic yard minimum load most plants will deliver, so you either pay a short-load fee or mix 33 bags. The 96 ft perimeter of a 24 × 24 ft garage is 3.5 cubic yards — 157 bags, about 6.3 short tons through your hands. That one is a truck.

One thing this calculator will not tell you: how wide and how deep the footing has to be. That depends on the load above, your soil's bearing capacity and your local code. Get those two numbers from your building department, then come back for the volume.

Common cases

Questions people ask

How much concrete do I need for a deck footing?
A 12 in diameter tube 36 in deep holds 2.36 cubic feet. With 10% waste that is 5 × 80 lb bags per pier. Six piers is 30 bags — over a tonne of material, which is the point at which most people start pricing ready-mix.
How much rebar overlap do I need at a splice?
Per IRC Table R608.5.4(1), Grade 60 bar needs 30 in for #4, 38 in for #5 and 45 in for #6. The "40 bar diameters" rule you will see quoted is the Grade 40 column of the same table, and Grade 40 is not what is on the rack.
How thick should a footing be?
Six inches is the IRC minimum (R403.1.1), and 8 in is the common build. Width matters more than thickness for bearing: the projection either side of the wall must be at least 2 in and no more than the footing thickness, so a thicker footing is what lets you make a wider one.
Can I pour a footing and the wall at the same time?
Not usually — you want the footing to set so you can build formwork on it, and the keyway or dowels between them are what tie the wall down. What you can do is pour a footing and a slab on the same truck visit if the forms for both are ready.
What about a footing on a slope?
IRC R403.1.5 requires the top of the footing to be level and the bottom to slope no more than 1 unit in 10. Beyond that you step the footing down the hill. Calculate each step as its own rectangle and add them — a single length × width × depth will underestimate a stepped footing.

Last reviewed